On the afternoon of October 26, Mr. Zhu Yejunjie, General Manager of the Group, and Mr. Luo Jun, Chairman of Ningbo Anjie New Energy Investment and Development Co., Ltd. formally signed an investment cooperation agreement on solar photovoltaic power generation project. After two months of intensive construction, the first phase of the project totaled 6.07 MW, which was completed on December 26 and passed before the Spring Festival. Expert acceptance work of Ningbo Power Supply Bureau and Hangzhou Bay New Area Power Supply Bureau was carried out.
On February 06, 2017, the electrical engineer of Ningbo Anjie New Energy Investment and Development Co., Ltd. and Hangzhou Bay New Area Power Supply Bureau jointly opened the power supply switch, marking the formal start of the first phase of photovoltaic power generation project grid-connected power generation.
In 2017, the second phase of photovoltaic power generation project in the park will be constructed. After completion, the total photovoltaic power generation in the park will reach about 7.5 MW.Prev: | Next: | Return |